Skip to main content
Loading…
This section is included in your selections.

Within 14 days after issuance of a determination of completeness, the city shall provide notice of the application which shall include the following:

A. The date of application, date of notice of completeness, and the date of notice of application;

B. A description of the proposed project action and a list of the project permits included in the application and, if applicable, a list of any studies requested under Chapter 14.06 or 14.11 ACC;

C. Identification of other permits not included in the application to the extent known by the city;

D. Identification of existing environmental documents that evaluate the proposed project, and, if not otherwise stated on the document providing the notice of application, the location where the application and any studies can be reviewed;

E. A statement of the public comment period, which shall be 15 days following the date of the notice of application together with a statement of the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal rights. The city may accept public comments at any time prior to the closing of the record of an open record predecision hearing, if any, or, if no open record predecision hearing is provided, prior to the decision on the project permit;

F. If applicable and scheduled at the time of the notice of application, the date, time, location and type of hearing;

G. A statement of preliminary determination, if one has been made at the time of notice of application, of those development regulations that will be used for project mitigation and of consistency as provided in Chapter 14.08 ACC;

H. Any other information determined to be appropriate by the city. (Ord. 4835 § 1, 1996.)