A. Unless specified elsewhere, an administrative or conditional use permit shall be implemented within two years of the approval. If a building permit or occupancy permit is required for the administrative or conditional use and has not been issued within the two-year period, then the administrative or conditional use permit shall be null and void.

B. The planning director or designee may grant one extension of the time period for implementation of the administrative or conditional use permit of up to 12 months following the submittal of a written request by the holder of the permit a minimum of 30 calendar days prior to the expiration date of the permit. (Ord. 6269 § 22, 2009; Ord. 4840 § 1, 1996; Ord. 4229 § 2, 1987.)