The city will conduct inspections as prescribed in the latest adopted copy of the International Building Code with the exceptions as noted below:

A. IMC/UPC/IFGC/NEC Rough-In Inspection. Rough-in mechanical, gas piping, plumbing and electrical shall be inspected when the rough-in work is complete and under test. No connections to primary utilities shall be made until the rough-in work is inspected and approved.

B. Energy Efficiency Inspection – Envelope.

1. Wall Insulation Inspection. To be made after all wall insulation and air vapor retarder sheet or film materials are in place, but before any wall covering is placed.

2. Glazing Inspection. To be made after glazing materials are installed in the building.

3. Exterior Roofing Insulation. To be made after the installation of the roof insulation, but before concealment.

4. Slab/Floor Insulation. To be made after the installation of the slab/floor insulation, but before concealment.

C. Special Inspections. In addition to the inspections specified above, the building official is authorized to make or require special inspections above the requirements as stated in Chapter 17 of the International Building Code for any type of work related to the technical codes by an approved agency at no cost to the jurisdiction. (Ord. 6902 § 6, 2023; Ord. 6763 § 3, 2021; Ord. 6601 § 10, 2016; Ord. 6469 § 2, 2013; Ord. 6310 § 7, 2010; Ord. 6104 § 6, 2007; Ord. 5874 § 4(109), 2004.)